PROJECT STORY
01 · OVERVIEW · MAIN CONTRACTOR
BUILT INTO A WORKING PORT.
As main contractor, M&B delivered the coordinated civil scope for the Wheels in Motion Weighbridge project at Fremantle Port.
The 12-week project required precise pavement and equipment interfaces, coordination of buried services and specialist subcontractors, and staged integration within a live operational environment.
CLIENT
DP World
VALUE
Approximately $500k
PROGRAM
12 weeks · Jan 2026
PREPARE EVERY INTERFACE.
02 · CIVIL WORKS
M&B installed conduits for communications and power, and completed the earthworks required for both rigid concrete pavement areas and flexible pavement areas.
Accurate levels and clean transitions connected the equipment zones, vehicle paths and surrounding surfaces.
03 · MANAGED DELIVERY
M&B managed the concrete, electrical and instrumentation subcontractors as part of its main-contractor role.
The scope also included bollard installation, bringing the civil works and specialist interfaces together for the completed operational lane.
COORDINATE TO COMPLETION.
OUTCOMES DELIVERED
Live port operations protected
Buried-service interfaces coordinated
Pavement levels and transitions controlled
Specialist subcontractors sequenced
Asphalt, compaction and concrete testing completed
No recordable injuries, quality issues or rework reported